If 15 workers did a job is 8 hours, how long would it take 5 workers to do half of this job?

Respuesta :

mrmetsman123 mrmetsman123
  • 09-04-2017
Since 15 workers did 8 hours of work, the total amount of work needed is 120 hours. Half of this job would be 60 hours. Then divide this amount by the 5 workers doing the job. This would make the job 12 hours
Answer Link
irspow
irspow irspow
  • 09-04-2017
J=15w*8h=120(worker*hours)

5h=120/2

5h=60

h=12 hours
Answer Link

Otras preguntas

Situation 1 John bought a new car. After driving it daily for several months, he gets a notice in the mail. The notice says that the car manufacturer has issued
round 779 to the nearest 10
Perimeter of a semi circle with diameter 30cm
Please help meee, i dont know how to solve these type of questions. Educate meee.
1 What typically happens to the inflation rate when unemployment falls to very low levels? O A It will rise or fall but not with the unemployment rate. OB It st
Jalynn and Emma enjoy hiking. Jalynn hikes 1 mile in 20 minutes. Emma hikes at a rate of 3 miles per hour. On Sunday at 8:00 a.m., they both left the trailhead.
how deep is the ocean?
3. Find the radius of a cylinder with a volume of 950 cm3and a height of 10 cm.​
Consider the regular octagon below with a center at the organ and a vertex at 4,0
speaking assertively when you feel disrespected is a strategy to stop ​