The detailed plan that shows the exact end items (i.e., finished products) to be produced in a specific time frame is known as what

Respuesta :

dmd459 dmd459
  • 11-02-2022

Answer:

Master Production Schedule (MPS)

Explanation:

Master production schedules are plans for individual products to be produced. The plans specify the time a specific product is produced, inventory needs, staffing needs, etc. A master production schedule or MPS will quantify raw materials, processes, and other resources needed to optimize production. (optessa.com)

Answer Link

Otras preguntas

why in summer water vapour rises upwards????????????? please I want the answer very fast
A barbed-wire barrier erected by the East Germans between East and West Berlin that eventually was rebuilt of concrete
what type of learning shapes innate behaviors?
The Intertropical Convergence Zone is _____. an escarpment an organization established to build dams an area rich in mineral deposits a low-pressure area that
why is death by predators more natural?
3/10 in.=7/8 mi. (i am doing rates and ratios)
What is a coalition? a temporary alliance of political parties a temporary military alliance a labor alliance
What were Ortoghs? Mongol provinces Chinese coins associations of caravan merchants Mongol boats
In Canada, the greatest concentration of Asians lives in which city? A. Montreal, QC B. Winnipeg, MB C. Ottawa, ON D. Calgary, AB E. Vancouver, BC
which is bigger 0.45 or 2/5