21. In the chart below, both suppliers have the same average lead time. If you want equivalent service levels against the planned lead time in your planning system for these suppliers, which of the following describes the lead time input to the planning system for these suppliers: a. Lead times for both suppliers should be the same b. Lead time for supplier 1 needs to be greater than lead time for supplier 2 c. Lead time for supplier 2 needs to be greater than lead time for supplier 1