How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?

Respuesta :

purplefries
purplefries purplefries
  • 07-11-2018
8 workers can complete a task in 10 days, meaning the man-hours needed to this task is 80 man-hours.

Hence for 5 workers to complete the same task that require 80 man-hours, 80÷5= 16.

So, it will take 16 days for 5 workers to complete this task.
Answer Link

Otras preguntas

What is the sum of the complex numbers below?(5+7i)+(-2+6i)A. -3 +13iB. 3+13iC. -3-13iD. 3-13i​
If two variables have a non-related relationship and one of the variables is changed, how will the other variable change? Increase Decrease No change Increase
Why does Odysseus remind his men of their fight with the Cyclops? He wants to remind them that they have defeated great monsters before. He wants them to use th
Roopesh has $24 dollars to spend on a birthday gift. The store where he is shopping has a sale offering $5 off the regular price, r, of any item. Write an inequ
What would cause the shape of a molecule to be tetrahedral? A. Three atoms bound to a central atom with one lone pair B. Four atoms bound to a central atom with
Need help with this problem
{(1,2), (-2,3), (1,3), (-2,2)} is what type of relation? A. one-to-many B. many-to-many C. one-to-one D. many-to-one
What is a requirement of supplementary angles?
what is potential difference​
During translation, the code for genetic information changes from--- A. Proteins to Amino Acids B. Amino acids to Codons C. Codons to Amino Acids D.Codons to